Roaring Meg
Power Station

PIPELINE DUPLICATION

Subcontractor

The scope of works is to install approximately 500m of 711x 5mm steel pipeline. This specification covers the installation of welded steel pipeline, including excavation, bedding, installation, jointing by welding, installation of fittings, replacement of paint coatings, back filling and reinstatement. The pipeline is to be installed in parallel to the existing pipeline that is above ground in places. The proposed pipeline route follows a vehicle track that has the existing pipeline located on the uphill side. The new pipeline generally will be installed buried on the down hill side of the track. During the construction of the new pipeline the existing is to remain in-service.